Certified Scrum Master (CSM) – GAQM — Question 33

How could the team and other stakeholders know if a product backlog item is done?

Answer options

Correct answer: B

Explanation

The correct answer is B because the definition of Done provides a clear and agreed-upon standard that the Scrum Team uses to assess the completion of backlog items. The other options do not provide a definitive measure of completion; simply asking individuals does not ensure adherence to the team's agreed standards.