Certified Scrum Master (CSM) – GAQM — Question 33
How could the team and other stakeholders know if a product backlog item is done?
Answer options
- A. They should ask to the member's development team
- B. They should compare what was done, against the definition of Done established by the Scrum Team
- C. Ask the Product Owner
- D. Ask the Manager
Correct answer: B
Explanation
The correct answer is B because the definition of Done provides a clear and agreed-upon standard that the Scrum Team uses to assess the completion of backlog items. The other options do not provide a definitive measure of completion; simply asking individuals does not ensure adherence to the team's agreed standards.