Certified Scrum Master (CSM) – GAQM — Question 26
Which of the following activities do not occur at the end of the Sprint? (Choose two)
Answer options
- A. Software development
- B. Release deployment
- C. Sprint review meeting
- D. Quality assurance testing
Correct answer: A, D
Explanation
Software development (A) and quality assurance testing (D) are ongoing activities that should be completed prior to the end of the Sprint. In contrast, release deployment (B) and the Sprint review meeting (C) are specifically scheduled to occur at the end of the Sprint to assess progress and prepare for the next phase.