Certified Scrum Master (CSM) – GAQM — Question 27

Who determines whether the development team has been assigned enough work in a Sprint?

Answer options

Correct answer: A

Explanation

The Development Team is responsible for determining their own workload during a Sprint, as they are the ones who understand their capacity and capabilities. The Product Owner focuses on prioritizing the backlog, while the Scrum Master facilitates the process but does not decide the team's workload.