Certified Scrum Master (CSM) – GAQM — Question 27
Who determines whether the development team has been assigned enough work in a Sprint?
Answer options
- A. The Development Team
- B. The Product Owner
- C. The Product Owner and the Scrum Master
- D. The Scrum Master
Correct answer: A
Explanation
The Development Team is responsible for determining their own workload during a Sprint, as they are the ones who understand their capacity and capabilities. The Product Owner focuses on prioritizing the backlog, while the Scrum Master facilitates the process but does not decide the team's workload.