Certified Scrum Master (CSM) – GAQM — Question 25
Under what circumstances should separate Product Backlogs be maintained?
Answer options
- A. There are several Product Owners for one product. Each Product Owner should have their own Product Backlog
- B. There are multiple teams working on independent products. Each unique combination of team and product should have an independent Product Backlog
- C. There are multiple product features being developed by the same team.
- D. There are multiple teams working on the components of the same product. Each team should an independent Product Backlog
Correct answer: B
Explanation
The correct answer is B because it emphasizes the need for independent Product Backlogs when different teams work on separate products, ensuring clarity and focus. Option A is incorrect as multiple Product Owners on a single product do not necessitate separate backlogs; option C is not relevant as it pertains to features rather than product independence; option D is incorrect because it suggests separate backlogs for teams working on the same product, which is not necessary.