CompTIA Project+ (PK0-005) — Question 95

A project team has identified a bug during user acceptance testing. Which of the following is the BEST method for communicating that bug to the development team?

Answer options

Correct answer: C

Explanation

Issuing a change request is the most appropriate method as it formally documents the need for modifications and ensures that the development team addresses the bug systematically. The other options, while they involve communication, do not provide the same level of formal acknowledgment and tracking needed for bug resolution.