CompTIA Project+ (PK0-005) — Question 96
Internal project team members and a subject matter expert had a heated discussion about the client's needs. The deliverable is now at risk of being delayed. Which of the following should be notified LAST?
Answer options
- A. Program manager
- B. End user
- C. Steering committee
- D. Project sponsor
Correct answer: B
Explanation
The end user should be notified last because they are typically the final audience for updates regarding project progress and changes. Informing the program manager, steering committee, and project sponsor first is crucial as they play key roles in decision-making and resource allocation that can help mitigate the delay.