CompTIA Project+ (PK0-005) — Question 77
In the kickoff meeting, a project manager announced the project will use a tool to store documents, artifacts, and any other data relevant to the project. The tool will perform version control, maintain retention data, and archive destruction or historical information. Which of the following is being described?
Answer options
- A. Record management system
- B. Project dashboard
- C. Backlog
- D. Wiki knowledge base
Correct answer: A
Explanation
The correct answer is A, as a Record management system is specifically designed to store and manage documents and artifacts while providing version control and retention capabilities. The other options do not provide the comprehensive data management features described; a Project dashboard focuses on project tracking, a Backlog is related to task management, and a Wiki knowledge base is primarily for collaborative information sharing.