CompTIA Project+ (PK0-005) — Question 78

During the planning phase, a project manager held a meeting to discuss meeting days, meeting times, meeting frequency, and tools to use. Which of the following will the project manager use to document this data?

Answer options

Correct answer: A

Explanation

The project communication plan is specifically designed to outline how project information will be communicated, including meeting schedules and tools. The project charter and project management plan are broader in scope and do not specifically focus on communication details, while the project plan is a general term that may encompass various aspects of the project but is not the designated document for communication strategies.