A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?
Answer options
- A. Performing
- B. Adjourning
- C. Forming
- D. Norming
Correct answer: D
Explanation
The correct answer is D, Norming, as the team is collaborating effectively and members are comfortable seeking help. The Performing stage (A) indicates high productivity and independence, which is not fully established yet. Forming (C) is an earlier stage where team members are just getting to know each other, and Adjourning (B) occurs at the end of the project, which is not applicable here.