CompTIA Project+ (PK0-005) — Question 63

During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Issue log, because it is specifically designed to document and track problems or concerns that arise during a project, including contract violations. The Time-tracking log (A) is used for monitoring hours worked and is not suitable for reporting issues. The Statement of work (C) outlines project deliverables and expectations but does not serve as a communication tool for issues. The Risk register (D) is for identifying and managing potential risks, not for documenting contractual breaches.