CompTIA Project+ (PK0-005) — Question 64
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
Answer options
- A. Create a list of tasks and share it with the team.
- B. Resend the scope of work to the team.
- C. Review the Gantt chart weekly with the team.
- D. Have the project sponsor meet with the team.
Correct answer: A
Explanation
Creating a list of tasks and sharing it with the team ensures that everyone knows their specific responsibilities, which directly addresses the confusion. Resending the scope of work may not clarify daily activities, while reviewing the Gantt chart weekly and having the project sponsor meet the team could still leave gaps in understanding individual tasks.