A project sponsor is notified that the committed turnaround time has been exceeded. The team member assigned to this item stated that the support of the management team was requested on time. Which of the following documents should be reviewed to understand the root cause of this situation?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Escalation path, as it outlines how issues should be raised to management for resolution, which is crucial in understanding why management support was not provided in a timely manner. The RACI (A) clarifies roles and responsibilities, the SOW (B) defines project deliverables, and the Communication plan (D) details communication strategies, but none directly address the escalation of issues.