CompTIA Project+ (PK0-005) — Question 60
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
Answer options
- A. Procurement
- B. Communication
- C. Quality assurance
- D. Risk
Correct answer: C
Explanation
The correct answer is C, Quality assurance, as it focuses on ensuring that the project's processes and outputs meet the required standards, thereby boosting team confidence and alignment with project goals. The other options do not specifically address the assurance of quality in the project deliverables or processes.