CompTIA Project+ (PK0-005) — Question 59
The project kickoff concluded, and the sponsor indicated that the recently hired summer interns are authorized to work on the project. Which of the following should the project manager do NEXT?
Answer options
- A. Host a risk workshop with all stakeholders to complete an initial risk assessment.
- B. Work with the interns to develop a work breakdown structure and project schedule.
- C. Conduct a skills assessment to determine the strengths and weaknesses of the staff.
- D. Assign the resources to project tasks and encourage them to begin work immediately.
Correct answer: C
Explanation
The correct answer, C, emphasizes the importance of understanding the interns' skills before assigning them tasks. This knowledge allows the project manager to leverage their strengths effectively. Options A, B, and D are premature actions that should occur after assessing the team's capabilities.