CompTIA Project+ (PK0-005) — Question 58
During the kickoff meeting, a stakeholder raises a concern that an assigned responsibility is outside of the stakeholder's domain. Which of the following would MOST likely be the reason?
Answer options
- A. The communication plan is outdated.
- B. The project manager did not assess the stakeholders.
- C. The project manager did not update the risk register.
- D. The statement of work does not reflect the impacted stakeholders.
Correct answer: D
Explanation
The correct answer is D because the statement of work should accurately outline the roles and responsibilities of all stakeholders involved in the project. If it does not, stakeholders may find themselves assigned tasks irrelevant to their expertise. The other options relate to different aspects of project management that do not directly address the concern of responsibility alignment.