CompTIA Project+ (PK0-005) — Question 57
Testing has been completed, and the new system is loaded in production and ready to be activated. Which of the following needs approval from the project sponsor?
Answer options
- A. Project charter
- B. Deployment plan
- C. Business case
- D. Release schedule
Correct answer: D
Explanation
The release schedule requires the project sponsor's approval as it outlines when the new system will go live, which is a critical decision point. The project charter, deployment plan, and business case are established earlier in the project lifecycle and do not need re-approval at this stage.