CompTIA Project+ (PK0-005) — Question 56
In an agenda for a kickoff meeting, some time is set aside to complete a document that identifies each member of the project, the members' roles and responsibilities for tasks, the milestones, and the key decisions. In which of the following should this data be documented?
Answer options
- A. TOR
- B. WBS
- C. RAM
- D. SOW
Correct answer: C
Explanation
The correct answer is C, RAM (Responsibility Assignment Matrix), as it specifically documents team members' roles and responsibilities related to tasks. TOR (A) refers to Terms of Reference, which outlines the purpose and scope of a project, while WBS (B) is a Work Breakdown Structure that breaks down project deliverables. SOW (D), or Statement of Work, outlines the work required for a project but does not detail individual roles and responsibilities.