CompTIA Project+ (PK0-005) — Question 55

Two projects share resources. The mobile application project cannot start if the database renewal project has not started. Which of the following relationships describes this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B, Start-to-start, because the mobile application project cannot commence until the database renewal project begins. The other options do not accurately represent this dependency; Finish-to-start (C) implies one project must finish before the other starts, while Start-to-finish (A) and Finish-to-finish (D) do not fit the described situation at all.