CompTIA Project+ (PK0-005) — Question 54
As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT?
Answer options
- A. Validate the change implementation.
- B. Implement the change.
- C. Conduct an impact assessment.
- D. Communicate the change deployment.
Correct answer: B
Explanation
The correct next step is to implement the change, as it follows the planning adjustments made in response to the change request. Validating the change implementation and conducting an impact assessment are typically done after the change has been executed, while communicating the change deployment is a subsequent step after implementation.