CompTIA Project+ (PK0-005) — Question 44
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?
Answer options
- A. Memorandum of understanding
- B. Request for information
- C. Statement of work
- D. Non-disclosure agreement
Correct answer: C
Explanation
The correct answer is C, Statement of work, because it outlines the specific requirements for the project, including the goods and services needed. The other options, while important, do not directly pertain to the immediate update required after identifying procurement needs.