CompTIA Project+ (PK0-005) — Question 43
Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?
Answer options
- A. Communicate with the affected stakeholders.
- B. Initiate a formal change request to modify the cost.
- C. Adjust the scope to stay within the cost.
- D. Set a new cost using a lightweight estimation method.
Correct answer: A
Explanation
The correct answer is A because communicating with the affected stakeholders is essential to understand their concerns and ensure alignment on the project's direction. Options B and C involve making changes that may not be feasible without stakeholder buy-in, while option D suggests a less formal estimation approach that may not provide an accurate budget assessment.