CompTIA Project+ (PK0-005) — Question 42
Which of the following criteria would favor using the agile methodology to manage an upcoming project?
Answer options
- A. Strong projectized organization
- B. Medium risk
- C. Lack of resources
- D. Multiple undefined tasks
Correct answer: D
Explanation
The correct answer is D because agile methodologies thrive in environments where tasks are not clearly defined, allowing for flexibility and iterative development. Options A and B suggest a more structured approach that may not require the adaptability offered by agile, while option C indicates a constraint that could hinder the implementation of agile practices.