CompTIA Project+ (PK0-005) — Question 45
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
Answer options
- A. Dashboard
- B. Gantt chart
- C. Work breakdown structure
- D. Requirements Traceability Matrix
Correct answer: A
Explanation
The correct answer is A, as a Dashboard provides a visual representation of project metrics and progress, making it ideal for updates to stakeholders. While a Gantt chart (B) shows timelines and tasks, it is less effective for high-level updates. A Work Breakdown Structure (C) outlines project tasks but does not present progress. The Requirements Traceability Matrix (D) tracks requirements but is not designed for progress reporting.