CompTIA Project+ (PK0-005) — Question 4

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Answer options

Correct answer: A

Explanation

The correct answer is A, Synchronous, as it facilitates real-time communication, allowing for immediate feedback and dynamic discussions. Options B (Informal) and D (Formal) refer to the style of communication rather than the immediacy, while C (Asynchronous) does not provide the quick interaction that the project manager desires.