CompTIA Project+ (PK0-005) — Question 5
Which of the following activities would a project manager perform during the closing phase? (Choose three.)
Answer options
- A. Lessons learned
- B. Risk analysis
- C. Removing resources
- D. Acquiring resources
- E. Statement of work sign-off
- F. Stakeholder analysis
- G. Removing access
Correct answer: A, C, G
Explanation
The correct activities during the closing phase include 'Lessons learned' to capture insights, 'Removing resources' to release team members and equipment, and 'Removing access' to ensure security. The other options, such as 'Risk analysis' and 'Acquiring resources,' are more relevant to the planning and execution phases of a project.