CompTIA Project+ (PK0-005) — Question 3
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
Answer options
- A. Status report
- B. Project plan
- C. Change log
- D. Meeting minutes
Correct answer: D
Explanation
The correct answer is D, as meeting minutes capture the key points discussed during the meeting, including assignments and decisions made, ensuring that absent members are informed. While a status report (A) provides an overview of the project's progress, it may not detail the specific assignments discussed in the meeting. A project plan (B) outlines the overall project scope and deliverables, but does not serve the purpose of updating team members on meeting discussions. A change log (C) tracks changes in project scope or requirements, but is not focused on meeting outcomes.