CompTIA Project+ (PK0-005) — Question 38

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)

Answer options

Correct answer: D, E

Explanation

The correct answers are D (Issue log) and E (Change log) because these documents are specifically designed to capture issues that arise during a project and any changes that need to be made as a result. The other options, such as the Risk report and Defect log, do not specifically address the recording of unexpected events and their work-arounds.