CompTIA Project+ (PK0-005) — Question 37

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Answer options

Correct answer: C

Explanation

The correct answer is C, as updating the project charter is essential after forming the project team to reflect the team's roles and responsibilities. Options A and B are important but occur later in the process, while D involves scheduling tasks which is also a subsequent step.