CompTIA Project+ (PK0-005) — Question 37
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
Answer options
- A. Determine budget constraints.
- B. Validate the business case.
- C. Update the project charter.
- D. Create a project schedule.
Correct answer: C
Explanation
The correct answer is C, as updating the project charter is essential after forming the project team to reflect the team's roles and responsibilities. Options A and B are important but occur later in the process, while D involves scheduling tasks which is also a subsequent step.