CompTIA Project+ (PK0-005) — Question 39
After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?
Answer options
- A. Implement the change.
- B. Approve the test plan.
- C. Notify customers.
- D. Develop a rollback plan.
Correct answer: D
Explanation
Developing a rollback plan is crucial as it provides a strategy to revert changes if something goes wrong during implementation. The other options, such as implementing the change or notifying customers, should only happen after ensuring a rollback plan is in place to mitigate risks effectively.