CompTIA Project+ (PK0-005) — Question 39

After determining the appropriate maintenance window, which of the following should occur NEXT in the operational infrastructure change process?

Answer options

Correct answer: D

Explanation

Developing a rollback plan is crucial as it provides a strategy to revert changes if something goes wrong during implementation. The other options, such as implementing the change or notifying customers, should only happen after ensuring a rollback plan is in place to mitigate risks effectively.