CompTIA Project+ (PK0-005) — Question 358
Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?
Answer options
- A. Avoiding
- B. Smoothing
- C. Forcing
- D. Compromising
Correct answer: A
Explanation
The project manager is using the Avoiding technique by deciding to postpone the meeting instead of forcing a resolution. This approach is appropriate when discussions become unproductive, allowing time for the developers to gather their thoughts. The other techniques, such as Smoothing, Forcing, and Compromising, involve attempts to resolve the conflict immediately rather than deferring it.