A stakeholder notices a typo in the project management plan, specifically the word manager was spelled “manger”. Which of the following is the decision maker who can authorize the change so the correction can be made?
Answer options
- A. PM
- B. CCB
- C. Sponsor
- D. Business analyst
Correct answer: A
Explanation
The correct answer is A, PM (Project Manager) because they typically have the authority to make changes to project documents. While the Change Control Board (CCB) and the Sponsor may also be involved in larger changes, a simple typo correction usually falls within the PM's purview. The Business Analyst typically focuses on requirements and may not have decision-making authority over document corrections.