CompTIA Project+ (PK0-005) — Question 357

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Answer options

Correct answer: B

Explanation

The correct answer is B because the project manager should assess how the new request will affect the current project parameters before proceeding. Option A is incorrect as it disregards the proper change management process, while C and D assume implementation without first evaluating the impact.