CompTIA Project+ (PK0-005) — Question 357
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
Answer options
- A. Decline because it is not included in the project scope.
- B. Assess the impact of the request and create a change request.
- C. Create new functional and non-functional requirements for mobile devices.
- D. Revise the baseline of the project plan by adding the new requirements.
Correct answer: B
Explanation
The correct answer is B because the project manager should assess how the new request will affect the current project parameters before proceeding. Option A is incorrect as it disregards the proper change management process, while C and D assume implementation without first evaluating the impact.