CompTIA Project+ (PK0-005) — Question 356
A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?
Answer options
- A. Build
- B. Subscription
- C. Lease
- D. Buy
Correct answer: B
Explanation
The subscription model allows flexibility in terms of user count, making it ideal for situations where the number of users is unknown. Building software can be costly and time-consuming, leasing may not provide the necessary scalability, and buying outright could lead to excess expenditure if user needs fluctuate.