CompTIA Project+ (PK0-005) — Question 355

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Answer options

Correct answer: B

Explanation

The Project Management Plan is the correct choice as it encompasses all aspects of the project, including requirements and stakeholder agreements. The Project Change Management Plan is focused on managing changes, the Project Transition Plan deals with transferring project deliverables, and the Project Communication Plan outlines communication strategies, none of which specifically document the input from stakeholder meetings regarding the minimum viable product.