CompTIA Project+ (PK0-005) — Question 325
A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?
Answer options
- A. Avoid injuries by using robots to perform tasks.
- B. Transfer risk to an insurance company.
- C. Mitigate risk by training the construction workers.
- D. Accept the risks inherent to construction.
Correct answer: C
Explanation
The correct answer is C, as training construction workers can significantly reduce the likelihood of injuries by ensuring they are aware of safety protocols and best practices. Option A, while beneficial, may not be feasible for all tasks; B only shifts the risk rather than addressing it directly; and D is not proactive in managing the risks that can be mitigated.