CompTIA Project+ (PK0-005) — Question 326

A team has just finished a major stage of a project. The project manager now has to evaluate the work completed up to this point, what tasks still need to be completed, and reassess risks and scope. Which of the following best describes what the project manager should perform?

Answer options

Correct answer: D

Explanation

The correct answer is D, Phase gate review, as it involves evaluating the project's progress at critical checkpoints. The other options do not encompass the comprehensive assessment of completed and outstanding tasks, as well as risk reassessment that a phase gate review entails.