CompTIA Project+ (PK0-005) — Question 324
Which of the following are considered core elements in a project closeout report?
Answer options
- A. Gap analysis of critical path
- B. Project scope, schedule, and cost
- C. Company vision, mission, and goals
- D. Results and outcomes of the project
Correct answer: D
Explanation
The correct answer is D because the results and outcomes of the project provide a summary of what was achieved and how it aligns with the initial objectives. Options A, B, and C, while relevant to project management, do not specifically pertain to the key elements required in a project closeout report.