CompTIA Project+ (PK0-005) — Question 323
During a project kickoff meeting, the project manager wants to set expectations for all of the team members. Which of the following actions should the project manager take to accomplish this goal?
Answer options
- A. Assign tasks and responsibilities to the team members.
- B. Provide an overview of the project objectives and timeline.
- C. Develop a project communication plan.
- D. Set a meeting cadence for the rest of the project.
Correct answer: B
Explanation
The correct answer is B because providing an overview of the project objectives and timeline gives the team a clear understanding of what is expected. Options A, C, and D, while important, do not directly address setting initial expectations for the team members.