CompTIA Project+ (PK0-005) — Question 31

During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?

Answer options

Correct answer: C

Explanation

The correct answer is C, SOW (Statement of Work), as it typically outlines project details including billing rates for resources. The SLA (Service Level Agreement), TOR (Terms of Reference), and NDA (Non-Disclosure Agreement) do not specifically provide information about client billing rates.