CompTIA Project+ (PK0-005) — Question 32
A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?
Answer options
- A. RFI
- B. RACI
- C. WBS
- D. SOW
Correct answer: B
Explanation
The correct answer is B, RACI, which stands for Responsible, Accountable, Consulted, and Informed, and is used to clarify roles and responsibilities in a project. Options A (RFI), C (WBS), and D (SOW) serve different purposes, such as requesting information, breaking down project tasks, and defining project scope, respectively, but do not specifically document task responsibilities.