CompTIA Project+ (PK0-005) — Question 302

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Answer options

Correct answer: C

Explanation

The correct answer is C, as project success criteria define the specific goals and deliverables that need to be met for the project to be considered successful, taking into account cost and time factors. The other options, while important, do not directly focus on defining the end goals and deliverables necessary for project success.