CompTIA Project+ (PK0-005) — Question 301
During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?
Answer options
- A. Some work packages are missing from the WBS.
- B. Information is missing from the RACI matrix.
- C. New knowledge bases were introduced.
- D. Team touch points are missing.
Correct answer: B
Explanation
The correct answer is B because a RACI matrix clarifies roles and responsibilities, and missing information can lead to confusion about task ownership. Option A is unlikely as missing work packages would not directly cause disagreement over assigned tasks. Option C is irrelevant as new knowledge bases do not inherently create conflict. Option D, while important, does not directly address the role clarity needed to resolve task disagreements.