CompTIA Project+ (PK0-005) — Question 303
Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?
Answer options
- A. Concept of operations
- B. WBS
- C. Integrated master schedule
- D. RACI
Correct answer: D
Explanation
The RACI matrix clearly outlines who is Responsible, Accountable, Consulted, and Informed for each task, making it the ideal artifact for understanding communication responsibilities. The other options, such as the WBS and integrated master schedule, focus more on project planning and scheduling rather than communication roles.