CompTIA Project+ (PK0-005) — Question 298
A project manager provided details regarding the completion of the following tasks:
• Vendor selection took less time than planned.
• Equipment procurement took less time than estimated.
• Equipment installation went according to schedule.
Which of the following should the project manager update?
Answer options
- A. Change log
- B. Project Gantt
- C. issue log
- D. Requirements traceability matrix
Correct answer: B
Explanation
The Project Gantt should be updated to reflect the changes in the timeline due to the quicker completion of vendor selection and equipment procurement. The Change log, issue log, and Requirements traceability matrix are not directly related to timing adjustments in the project schedule.