CompTIA Project+ (PK0-005) — Question 299
A project manager needs to develop a way to control who can modify documents, artifacts, and other data related to the product. Which of the following would be the best way to accomplish this objective?
Answer options
- A. Define access requirements.
- B. Develop a transition plan.
- C. Create a responsibility assignment matrix.
- D. Create a work breakdown structure.
Correct answer: A
Explanation
The correct answer is A, as defining access requirements establishes clear guidelines for who can modify documents and data. Options B, C, and D do not directly address the control of modifications, focusing instead on planning, responsibility, and task breakdown, which are not relevant to access control.