CompTIA Project+ (PK0-005) — Question 278
A member keeps bringing up unrelated topics during a team meeting. Which of the following should the project manager do to keep the discussion on track?
Answer options
- A. Remind the team member about the meeting agenda and invite the member to add the topic to the next meeting’s agenda.
- B. Ask the team member to leave the meeting and create a new meeting to discuss these topics.
- C. Adjust the current meeting’s agenda to accommodate the team member’s topics.
- D. Allow the team member to bring up the topics, which could lead to important discussions and insights.
Correct answer: A
Explanation
The correct answer is A because it addresses the issue by refocusing the discussion on the planned agenda while also acknowledging the team member's interests for future discussions. Options B and C are not ideal as they either disrupt the meeting unnecessarily or shift the agenda inappropriately. Option D may lead to chaos and distract from the meeting's objectives.