CompTIA Project+ (PK0-005) — Question 279

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

Answer options

Correct answer: B

Explanation

The correct answer is B because identifying business needs and product descriptions is essential for understanding the project's objectives and requirements before any other planning can take place. The other options, while important, come after the initial identification of business needs.