CompTIA Project+ (PK0-005) — Question 277

During an active project, the finished product is not meeting quality specifications. Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

Answer options

Correct answer: C

Explanation

The correct answer is C, as creating a change request is a formal way to document the need for change and initiate the process. Options A and B are part of the communication and documentation process but do not initiate change. D is premature because the changes must first be formally requested and approved.