CompTIA Project+ (PK0-005) — Question 265
A project manager learns that a handful of resources from the project were pulled off the project to work on a higher priority project. The project manager had previously captured this information based on indicators of this potential change. Which of the following is the sequence of these events?
Answer options
- A. Issue, issue
- B. Issue, risk
- C. Risk, issue
- D. Risk, risk
Correct answer: C
Explanation
The correct answer is C, as the situation began as a risk when the potential for resource reassignment was identified. When the resources were actually pulled from the project, it became an issue. The other options incorrectly classify the sequence of events or do not accurately represent the transition from risk to issue.