CompTIA Project+ (PK0-005) — Question 266
A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables. Which of the following should the project manager do first?
Answer options
- A. Review the project risk register.
- B. Update the defect tracker.
- C. Meet with stakeholders to discuss concerns.
- D. Add the potential blockers to the issues list.
Correct answer: A
Explanation
The correct answer is A because reviewing the project risk register allows the project manager to assess known risks and identify any additional risks that may not have been previously documented. The other options, while important, do not address the immediate need to understand the project's risk landscape before taking further action.