A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables. Which of the following should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A because reviewing the project risk register allows the project manager to assess known risks and identify any additional risks that may not have been previously documented. The other options, while important, do not address the immediate need to understand the project's risk landscape before taking further action.